How long does an apartment renovation take

A full apartment renovation usually takes 2–5 months, and the bathroom alone 2–4 weeks. The timeline depends above all on the scope – whether the installations are replaced – on the drying time of screeds and plaster, and on how many decisions have been made before the start.

Apartment during a renovation with a schedule on the wall

Preparation, before the team moves in: a site visit, a written quote, the contract and ordering the materials with long delivery times – tiles, sanitaryware, doors, the kitchen. This phase is often underestimated. When it is skipped, the renovation starts without a plan and is already running late by the halfway point.

Strip-out: removing the old tiles, flooring and fittings, sometimes knocking down partition walls, and taking the waste away. This is where the real condition of the installations shows and where the ‘unforeseen’ work appears – corroded pipes, damp, old patch repairs. With us, extra work only starts after written approval and with a price.

Installations: new water pipes and drainage, new wiring and a consumer unit, testing. This is the most critical stage – a badly installed system can only be put right by breaking open finished walls and floors. That is why new pipes are pressure-tested before the wall is closed.

Walls, ceilings and screeds: plaster, plasterboard, skim coat, waterproofing in the wet rooms and self-levelling screed. Each layer needs time to dry, and this cannot be cut short without consequences for the result.

Floors and tiling: tiles in the bathroom, toilet and kitchen, laminate or parquet in the rooms. This is where the visible result takes shape, so the work is not rushed.

Finishing work: doors, sanitaryware and taps, switches, sockets and lighting, skirting boards and cleaning. At the end we go round the property together, put right any remarks and hand it over with a signed record.

What makes it take longer: a late delivery, changes in the middle of the renovation and hidden defects after the strip-out. That is why the stage-by-stage schedule is in the written quote – it shows when each stage finishes, and the move-in date is planned from the last stage, not from the first day.

The RemontS promises

Six promises you can check

A renovation should not be stressful. This is what we do on every project — on paper and in front of you.

Book a free site visit
  1. A budget that does not change

    A written quote with the work, quantities and prices, then a contract for the same amount. Extra work starts only with your written consent and a price.

  2. You pay for work that is done

    Four instalments tied to the stages: 30% at signing, 30% after the rough work, 30% at 80% completion and the last 10% after you accept the property.

  3. A warranty on paper

    2 years' warranty on all work, 6 years on plumbing, electrical and roofing work, with a written certificate.

  4. Tested before it is closed

    New pipes are pressure-tested before they go into the wall. Waterproofing is tested with water before any tiles go on.

  5. Clean every day, handover with a record

    Waste leaves the site every day and never stays in the stairwell. At the end we walk the property together and hand it over with a signed handover record.

  6. One team, one contract

    Our own full-time team for plumbing, electrical work, tiling, plastering and painting. You do not have to find or coordinate separate tradesmen.

The first step is a free, no-obligation site visit. A colleague calls you within 3–4 hours during working hours (Mon–Fri 9:00–18:00, Sat 10:00–14:00).

Ready for the next step? Book a site visit

The site visit and the written quote are free and with no obligation — we reply to your enquiry within 3–4 hours.

  • Free site visit
  • Written quote
  • Written warranty