Office renovation: labour costs and staying open during the work

A worked example for an 80 m² office – walls, partition, ceiling, lighting and floor – the choices that change it and how to renovate while staying open.

Free site visit and quote

Leave your phone – we will call you

+ Email and details (optional)

or +359 888 802 618 · Viber

−10% for contracts signed by 31 Dec 2026

By submitting you agree that we may contact you about your project. See our privacy policy.

A garage in Mladost before, during and after the renovation: stained walls, skim coating, and white walls with a red stripe

An office renovation is priced task by task. The labour price for the full process on the walls – primer, skim coat and paint – is €27.92 per m², for a suspended plasterboard ceiling €18.79 per m², and for one electrical point €32.21. In the worked example below, an 80 m² office with a new partition wall, a suspended ceiling, 36 electrical points and a new floor comes to €12,819.58 for labour, excluding materials.

We do not give a general per-square-metre guide for offices: in one office everything is replaced, in another only the paint and the lighting. The price for your office is in the written quote after the site visit.

Below are the calculation line by line, the decisions that change it most, and how to plan a renovation in stages if the office has to keep working during the renovation. The prices are as of October 2026 and may change; the current ones are in the price list.

Worked example: an 80 m² office

The example is for an 80 m² office in an existing building – a single space of about 10 × 8 m with a 2.8 m ceiling. The old carpet comes up, a plasterboard partition wall separates off a meeting room, a suspended plasterboard ceiling is built over the whole office, and laminate flooring is laid. The quantities are illustrative; for your office they will be different.

The new wall is 5 m long, or 5 × 2.8 = 14 m². The walls to be skim coated and painted come to 120 m², including both sides of the new wall. There are 36 electrical points: 20 sockets for the workstations, the meeting room and the equipment, 12 lighting points for the light fittings and 4 switches. The main items are also on our office renovation page.

Walls and partition wall

TaskQuantityLabour price
Walls: primer + 3 coats of skim + paint (full process) – €27.92 per m²120 m²€3,350.40
Building a plasterboard partition wall + tape and mineral wool – €32.21 per m²14 m²€450.94
Jointing plasterboard + mesh (both sides of the wall) – €5.37 per m²28 m²€150.36
Building a door opening in plasterboard – €200.00 each1 opening€200.00
Fitting an interior door – €100.00 each1 door€100.00
Total€4,251.70

Ceiling, electrical points and lighting

TaskQuantityLabour price
Installing a suspended plasterboard ceiling – €18.79 per m²80 m²€1,503.20
Jointing plasterboard + mesh – €5.37 per m²80 m²€429.60
Primer before skim coat, 2 coats of skim, sanding, dust removal, primer before paint, 2 coats of paint (ceiling) – €22.55 per m²80 m²€1,804.00
Electrical installation per point – €32.21 each36 points€1,159.56
Installing a light fitting – €35.00 each12 fittings€420.00
Total€5,316.36

Floor, waste and cleaning

TaskQuantityLabour price
Removing floor covering (carpet/vinyl) – €7.50 per m²80 m²€600.00
Self-levelling floor screed up to 3 cm – €20.00 per m²80 m²€1,600.00
Laying laminate flooring – €6.98 per m²80 m²€558.40
Fitting skirting boards – €4.29 per lin. m44 lin. m€188.76
Taking construction waste to a disposal site (tipper lorry) – €110.00 each2 trips€220.00
Cleaning and handing over the site – €84.36 each1 item€84.36
Total€3,251.52
Labour only, based on the price list as of October 2026; materials are not included.

In total: €4,251.70 + €5,316.36 + €3,251.52 = €12,819.58 for labour. The largest part is the ceiling with the electrical points and lighting – €5,316.36. The ceiling alone, without the points and the light fittings, is €1,503.20 + €429.60 + €1,804.00 = €3,736.80 for labour.

A ceiling during the renovation: metal profiles, strips of plasterboard along the walls and mineral wool between the profiles at the edge
A suspended plasterboard ceiling during the renovation – in the living room of a home, not an office: metal profiles, plasterboard along the walls and mineral wool. In an office, the ceiling is built under the same price-list items.

What changes the total

Three decisions move the calculation the most: what is done to the walls, what kind of ceiling you choose and what kind of floor. Which option suits you depends on the condition of the office and is decided at the site visit.

The walls

Walls with holes from shelving and traces of earlier renovations need the full process – €27.92 per m² for labour. For sound walls with minor defects, the lighter package ‘2 coats of primer – 1 skim coat – sanding – spray painting’ may be enough – €17.45 per m² for labour. And if the walls are smooth and you only want to freshen them up, ‘Spray painting – walls’ is €5.37 per m² for labour.

For 120 m², the difference is large: 120 × €27.92 = €3,350.40, 120 × €17.45 = €2,094.00 or 120 × €5.37 = €644.40 for labour. We explain how many coats of skim are needed, and when, in our article skim coating and painting: prices per m².

A long, narrow room with stains on the walls and ceiling, a bare bulb, an old shelf on the back wall and buckets on the floorBefore
The same room during the renovation: the walls have been skim coated in patches, cables hang from them, and there are buckets and a dismantled wooden shelf on the floorSkim coat
The same room after the renovation: white walls with a red stripe and a black lower section, a light-coloured floor and cables for the lightingAfter
The garage in Mladost is not an office, but its walls go through the same stages – skim coat and paint. From left to right: before the renovation, during skim coating and after painting.

The ceiling

A finished plasterboard ceiling – frame, jointing, skim coat and paint – is €18.79 + €5.37 + €22.55 = €46.71 per m² for labour. A grid ceiling is €21.47 per m² for labour and is not skim coated. For 80 m², that makes 80 × €46.71 = €3,736.80, compared with 80 × €21.47 = €1,717.60 for labour.

A grid ceiling looks more utilitarian, but its tiles lift out, so the cables above them stay accessible. Plasterboard gives a smooth ceiling that can conceal LED lighting, as in the living room with a suspended ceiling in the photo below. The types of suspended ceiling and the labour cost of concealed lighting are covered in our article on suspended ceilings with LED lighting.

A two-level suspended ceiling: a lower band along the walls with concealed LED strip and recessed downlights, with blue walls
The finished suspended ceiling in the same living room: LED strip concealed in the edge of the lower level and downlights in both levels.

The floor and the partition wall

If the base under the carpet is level, the self-levelling screed can be left out – that is €1,600.00 less for labour. If you choose SPC planks instead of laminate, fitting them is €20.00 per m² for labour: 80 × €20.00 = €1,600.00 instead of €558.40.

Without mineral wool, the partition wall is ‘Building a partition wall – plasterboard’ – €26.84 per m² for labour, or 14 × €26.84 = €375.76 instead of €450.94. For a meeting room, the wool makes sense: it reduces noise between the rooms, although it does not stop it completely. All the types of partition wall and wall lining are in our article on plasterboard prices, and how we work with plasterboard is on our page about plasterboard in Sofia.

How to keep working during the renovation

There are two ways. The office closes for the duration of the renovation – that is how the work goes fastest. Or the renovation is done in stages, zone by zone, while your team works in the rest of the space. Which approach suits you, and the stage-by-stage schedule, are agreed in the quote.

If the office stays open during the renovation, plan a few things in advance:

  • The zones. The area being worked on is cleared, and whatever stays in it is covered. The price list has items for this too: moving furniture is €80.00 for labour, and covering with plastic sheeting €40.90 for labour; what they will cost with your schedule is shown in the quote.
  • Noise and dust. Removals, cutting chases in the walls and sanding the skim coat make noise and dust, while painting and laying the laminate make much less. That is why the noisy stages are planned to disrupt your work as little as possible.
  • Power and internet. When work is being done on the electrical installation, the power to that zone is switched off. Decide in advance where the router and any equipment that must run without interruption will go. Network cabling is not an item in the price list – if it is being replaced, mention it at the site visit so that its routes can be planned together with the electrical points.
  • The building’s rules. In an office building, ask the building manager when work is allowed and which way materials and waste should go in and out. If the office is in a residential building, the renovation rules for apartment buildings with an owners’ association also apply.
  • Cleanliness. The waste is taken out every day, and at the end the site is cleaned and handed over – in the worked example, that is ‘Cleaning and handing over the site’, €84.36 for labour.

The stage-by-stage schedule is written into the quote. If, during the work, something outside the quote turns out to be needed, it is approved in writing, with a price, before it starts.

What the calculation leaves out

  • Materials. The plasterboard, profiles, primers, screeds, adhesives and mesh appear in our quote on a separate line. Who supplies the laminate and the door is agreed in the quote. Light fittings, switches and sockets are also materials and are not included in the amounts.
  • Chases in masonry walls. In the new wall and above the suspended ceiling, the cables run without any chasing, but brick and concrete walls need chases – €6.98 per linear metre in brick and €12.00 in concrete, for labour. What else the electrical work involves is covered in our article on electrical work prices.
  • The consumer unit. ‘Replacing a consumer unit, up to 8 fuses’ is €143.16 for labour; if the office needs a larger one, it is priced in the quote.
  • The kitchenette and the toilet facilities. If they are part of the renovation, they are priced under their own items – tiling, plumbing, installing the sanitaryware.
  • Furniture. Who supplies and installs the office furniture is agreed in the quote.

Frequently asked questions

Can the office stay open while the renovation is under way?

Yes, if the renovation is done in stages, zone by zone. Which zones, in what order and on what timescale is agreed in the quote.

Do you work with a contract and issue invoices?

Yes. The scope, the price and the schedule are set out in a contract, and you receive invoices for your payments. What to check in the quote before you sign is covered in our article why a written quote matters more than a low price.

How long does an office renovation take?

It depends on the scope and on whether the office stays open during the renovation. The skim coat and screed need time to dry, and that should not be cut short. The stage-by-stage timescale is in the quote after the site visit.

Who supplies the furniture?

We agree this in the quote. It is best to have the furniture chosen before work starts: the sockets and the lighting at the workstations are planned around it.

What is the warranty?

The warranty is in writing: 24 months for the renovation and 72 months for the plumbing and electrical installations.

If you are planning an office renovation, book a site visit. The site visit is free, and afterwards you receive a written quote with the work, the price and the stages set out. We work in Sofia and within about 80 km of it, as well as in Varna, Burgas, Plovdiv, Pleven and Blagoevgrad. We reply to enquiries within 3–4 hours.

The RemontS promises

Six promises you can check

A renovation should not be stressful. This is what we do on every project — on paper and in front of you.

Book a free site visit
  1. A budget that does not change

    A written quote with the work, quantities and prices, then a contract for the same amount. Extra work starts only with your written consent and a price.

  2. You pay for work that is done

    Four instalments tied to the stages: 30% at signing, 30% after the rough work, 30% at 80% completion and the last 10% after you accept the property.

  3. A warranty on paper

    2 years' warranty on all work, 6 years on plumbing, electrical and roofing work, with a written certificate.

  4. Tested before it is closed

    New pipes are pressure-tested before they go into the wall. Waterproofing is tested with water before any tiles go on.

  5. Clean every day, handover with a record

    Waste leaves the site every day and never stays in the stairwell. At the end we walk the property together and hand it over with a signed handover record.

  6. One team, one contract

    Our own full-time team for plumbing, electrical work, tiling, plastering and painting. You do not have to find or coordinate separate tradesmen.

The first step is a free, no-obligation site visit. A colleague calls you within 3–4 hours during working hours (Mon–Fri 9:00–18:00, Sat 10:00–14:00).

— Ready for a project? —

Book a site visit — reply within 3–4 hours

Briefly describe the property and you will receive a specific next step — with no obligation.

Enquiry

Tell us a bit about your project

One clear form, with no steps and no unnecessary questions. Send the main details and you will receive a personal reply.

Reply within 3–4 hoursA clear first outlineNo unnecessary steps
+ More details (optional)Not required — fill in only if you want a more precise reply.

By submitting you agree that we may contact you about your project. See our privacy policy.

Reply within 3–4 hours
Free site visit
Experience since 2019